Reconstruction at Freeport LNG Liquefaction Nearly Completed
Facility construction should be completed by end of November 2022.
Freeport LNG Development, L.P. today provided an update on the ongoing reconstruction and resumption of operations at its natural gas liquefaction and LNG export facility. As of November 14th, the reconstruction work necessary to commence initial operations, including utilization of all three liquefaction trains, two LNG storage tanks and one dock, was approximately 90% complete, with all reconstruction work anticipated to be completed by the end of November. Proposed remedial work activities for a safe restart of initial operations have been submitted to the relevant regulatory agencies for review and approval. Subject to Freeport LNG meeting its regulatory requirements, it is targeting initial production at the facility in mid-December.
Each of Freeport LNG's three liquefaction trains will be restarted and ramped up safely, in a slow and deliberate manner, with each train starting separately before restarting a subsequent train. It is expected that approximately 2 billion cubic feet (BCF) per day of production will be achieved in January 2023. Full production utilizing both docks remains anticipated to commence in March 2023.
"Our teams have worked diligently over the last several months alongside regulators to ensure the safe restart of our facility. I am immensely grateful for their efforts," said Michael Smith, founder, chairman and CEO. "We are committed to moving forward with an uncompromising safety focus and enhanced operational processes that will enable us to chart a safe, sustainable path forward to serve our customers and the broader LNG market as a whole."
RELATED CONTENT
-
Grappling with the World's Complex Energy Transition Through an ESG Lens
With a long list of contributing factors, the world is barreling headlong into an energy transition that’s full of challenges, opportunities and lofty net-zero goals.
-
MSS Publishes Revised and New Industry Standards
The Manufacturers Standardization Society (MSS) of the Valve and Fittings Industry is excited to announce publication of the new Standard Practice SP-158-2021, Supplemental High-Pressure Gas Test Procedures for Valves.
-
New Technologies Solve Severe Cavitation Problems
An advanced anti-cavitation control valve design enabled by 3D metal printing solved a power plant’s severe cavitation problem and dramatically improved its bottom line.